Project: TPP2 May 2014 Turnaround

Location: Lotte Chemical Titan (M) Sdn Bhd, Pasir Gudang

Job scope: 

Dismantle 30units of equipment motor from site for reconditioning job & reinstall, realign, reconnect & testing commissioning.

Duration: 8 days


Project: Malaysian Sheet Glass Cold Repair JB2F 2015

Location: Malaysian Sheet Glass Sdn Bhd, Pasir Gudang

Job Scope: 

  • Service & overhaul for 25 units of Main Cooling Fan & Cooling Fan Motor for Furnace & Tin Bath.
  • Installation 2 set of New Fan Set & Ducting Job

Duration: 21 days


Project: Upgrading of Automatic Silo System

Location: STO Sea Sdn Bhd, Seri Alam

Job scope: 

  • To upgrade the existing OPC, White & CC Cement automatic feed in & weighing system.
  • To design & construct monitoring system for New Silo.

Duration: 12days


Project: Explosive Proof Wiring for New Loading System of New Storage

Location: NPBT, Johor Port Pasir Gudang

Job scope: 

  • Cabling job for Transfer Pump & Chiller System
  • To design & construct Loading Bay Monitoring & Loading System for New Storage.

Duration: 20 days